A field map shows where manure may go and where it may not. This guide turns a farm sketch into net spreadable acres, a gallon total and a load count, so the crew knows each field before the tanker leaves the yard.

Why it matters

Crews lose time and risk violations when buffers, wells and wet spots live only in one person's head. A marked map settles them in advance. Setbacks and rules vary by state and by your nutrient management plan, so confirm each exclusion with your state agency, NRCS or certified planner.

Step by step

  1. Start with an aerial photo or plat for each field and write the gross acres on it from your plan or a measured boundary.
  2. Shade every exclusion in your plan, such as streams, ditches, wells, sinkholes, tile inlets, steep slopes and neighbors, using the distances your planner gives you.
  3. Mark gates, lanes, turnarounds, overhead lines and soft ground so drivers can plan passes and avoid ruts.
  4. Subtract the shaded acres from gross acres to get net spreadable acres, and write that number beside each field.
  5. Multiply net acres by the planned gallons per acre to get field gallons, then divide by tanker size and round up for loads.
  6. Number the fields in the order you will work them, putting the most sensitive field on a day with dry soil and no rain forecast.

Worked example

Illustrative: A field has 36 gross acres. The plan shades 2.5 acres along a creek, 1.5 acres around a well and 3 acres of steep slope, so net acres are 36 - 2.5 - 1.5 - 3 = 29. At a planned 4,000 gallons per acre the field takes 29 x 4,000 = 116,000 gallons. A 5,000 gallon tanker needs 116,000 / 5,000 = 23.2, so 24 loads, with the last load only about one fifth full.

Printable worksheet: manure spreading field map

  • Field name and gross acres: ____________ / ______
  • Exclusion acres (water, well, slope, other): ______ + ______ + ______ = ______
  • Net acres = gross - exclusions: ______
  • Planned gallons per acre ______ ; field gallons = net acres x rate: ______
  • Tanker size ______ ; loads = field gallons / tanker, rounded up: ______
  • Gate, lane and soft spot notes: ____________
  • Work order number and planned date: ______

Common mistakes

  • Using gross acres for the load count, which over-orders hauling and puts manure on ground the plan excluded.
  • Drawing the map once and never updating it after a new well, tile line or fence change.
  • Rounding the last partial load away and then dumping the leftover on the nearest convenient spot.
  • Mapping from memory instead of from the plan, so drivers and planner work from different boundaries.

Frequently asked questions

Where do I get exclusion distances?

From your nutrient management plan, which follows your state rules and NRCS standards. Ask your state agency, extension office or certified planner, and never copy distances from another state or an old map.

Should the map show soil test results?

It helps. Writing the phosphorus level and planned nutrient source beside each field lets the crew see why one field gets less. Keep the full numbers in your plan and update the map after each soil test.

Who should carry a copy?

Every driver and the person running the spreader, plus a copy in the office. A laminated map in the cab beats a phone call from a field gate, and old copies should be pulled when the plan changes.

Official sources

Educational only. Permit, setback and application rules vary by state; confirm with your state agency, NRCS and a certified planner. State dairy waste resources.